Projects in the works 2023:  
Roadmap for implementation of 80MW solar power generation project

Name of works

Time period

1) Formation and completion of the questionnaire.

25.09.2023

 

 

15.10.2023

2) Formation of Terms of Reference:

15.10.2023

a) Holding working meetings on the part of the contractor: Ismailov

V., Korogodsky A., Kopylov V., Armeyev D., on the side of the customer:

15.11.2023

Customer and authorized representatives of the Ministry of Energy of South Africa.

b) Formation of the Terms of Reference on the basis of the filled out

questionnaire and results of the conducted working meetings.

 c) Signing of the agreed terms of reference for the 80 MW project.

3) Creating a technical design.

15.11.2023

 

 

01.02.2024

4) Creation of a detailed design including detailed description and

01.02.2024

albums of technical documentation.

 

10.05.2024


Technical implementation of the 80 MW project

Name of works

Time period

1) Ordering of equipment according to the technical design and working documentation.

01.02.2024 

01.06.2025

2) Calculation and ordering of distribution networks and systems depending on the remoteness of the energy generation system (electricity and heat) to consumers.

-

3) Conclusion of a contract with the Ministry of Energy for operation and maintenance of the plants.

01.02.2024 

01.06.2025

4) Preparation of the site for the installation of the power plant:
 a) Preparation of foundations for each plant and distribution equipment
b) Connection of the power distribution network to the generating site
c) Organization of equipment logistics to the site for commissioning and start-up works
c) Conducting commissioning
d) Testing of the plants according to the scheme approved in the detailed design.

 

 



10.05.2024 

10.07.2025

e) Start of commissioning of the first units arriving during the manufacturing process of the entire batch. Arrival of the first plant

20.05.2024

5) Final commissioning of the last plants that came during the manufacturing process of the whole batch. Final commissioning of the power plant.

20.07.2025

6) Organization of acceptance by the customer's commission.

20.08.2025

7) Additional section on application of additional CSP-based SES options (included optionally, at the Customer's request):
1. Establishment and commissioning of treatment devices (powered by thermal energy from CSP units) to treat water in the mine processes to separate costly toxic elements into a solid fraction for reuse in the process and to prepare water for agricultural use.
2. Creation and commissioning of refrigeration units (operating on thermal energy from CSP units) for air cooling in working and production premises of the Customer.

 